Nutting Road Infrastructure Improvements

Update 4/21/2023:

Aqua Line Utility will return to Nutting Road tomorrow Saturday 4/21/2023 to complete the final loam and seed and clean up of the project area.

Project Description:

Ahead of the resurfacing of Nutting Road, the City will be rehabilitating the underground infrastructure along the roadway.  The City has contracted Aqua Line Utility of Weymouth, MA to complete this project.  Work will include cleaning and lining of the existing water main from Lake Street to College Farm Road and all required utility service repair.  After the utility work has been completed crews will prepare to mill and pave the roadway.  We expect this project to be completed by the Fall of 2023.

Work hours will be 7:00am – 4:00pm.  Please be on the lookout for No Parking signs posted ahead of work each day.

Should you have any questions, you can call us at 781-314-3830 or e-mail at jmartino@city.waltham.ma.us.