MWRA Water Main Project - Lexington Street
The Massachusetts Water Resources Authority (MWRA) will be installing a new 36" water main along Lexington Street from Piety Corner to the Lexington Town line. For more information regarding this project, please visit the MWRA's project website here.
Residents are encouraged to sign up for text / email alerts regarding this project through the MWRA's Everbridge service. You can sign up for these alerts online here
All questions and concerns regarding this project can be directed to Georges Makso or Troy Wall of the MWRA:
- Georges Makso - MWRA Onsite Representative
Phone: 857-331-4077
Email: Georges.Makso@mwra.com
- Troy Wall - MWRA Public Affairs
Phone: 617-305-5762
Email: troy.wall@mwra.com
CONSTRUCTION WEEK OF 5/13/2024 - 5/17/2024:
Massachusetts Water Resources Authority Notification
Construction activities for the week of May 13, 2024:
• This week, crews continued to make progress on the 36” water main by constructing approximately 23 linear feet of pipeline near Jack’s Way, installing a valve chamber and associated piping, and completing pipe work at the air release chamber.
o Crews were also able to focus on water main relocations/replacements on Lexington Street at the Lake Street intersection and Brookway Road intersection. At these locations gravel trenches were plated or paved ahead of weekend travel use.
o Additionally, full-width asphalt milling and grading along Lexington Street from Totten Pond Road to approximately 200 feet south of Jack’s Way was completed (the roadway is gravel through this location).
• Next week, crews will work a normal schedule with the southbound Lexington Street detour in place, Monday through Thursday, from 7:00AM to 5:00PM, with potential for work later each day or on Friday should weather or other impacts cause the schedule to shift.
o The crews are expected to continue installing the new 36” pipeline through Jack’s Way. They will also continue to address water main tie-ins at cross streets north of Lake Street.
o Furthermore, paving operations are currently scheduled to take place on Tuesday and Wednesday next Week (5/14 – 5/15).
Attachment | Size |
---|---|
MWRA Water Main Project Lexington St - Flyer | 100.04 KB |
MWRA Water Main Lexington Street - DETOUR PLAN (DAYS) | 5.22 MB |
MWRA Water Main Lexington Street - DETOUR PLAN (WHS) | 5.24 MB |