Water Main Replacement at Gale, Ripley, Peirce, and Clark Streets, 2023

CONSTRUCTION UPDATE (5/3/2024)

  • Week of 5/6/24 – 5/10/24
  • Construction Schedule
    • Monday – Friday 7:00 AM to 4:00 PM

**IN THE EVENT YOU ARE WITHOUT WATER WHILE CONNECTED TO THE TEMPORARY WATER SYSTEM, PLEASE CALL N. GRANESE’S 24/7 RESPONSE FOR ASSISTANCE: 978-210-4881

Clark Street:

  • THERE WILL BE NO SCHEDULED CONSTRUCTION THIS WEEK UNTIL THE WEEK OF 5/20.
  • Installation of water services will be the week 5/20.
  • Please be aware of “NO PARKING” signs on the street.
    • Note: When the signs on the barrel cones are facing out towards the street “NO PARKING” will be in effect on the posted signs. When the signs on the barrel cones are facing towards the houses, “NO PARKING” will be in effect.
  • Residents should anticipate slight delays on your commute times.

Ripley Street:

  • THERE WILL BE NO SCHEDULED CONSTRUCTION THIS WEEK UNTIL THE WEEK OF 5/20.
  • Installation of the new water main will begin after Peirce Street water main has been completed.
  • Please be aware of “NO PARKING” signs on the street.
    • Note: When the signs on the barrel cones are facing out towards the street “NO PARKING” will be in effect on the posted signs. When the signs on the barrel cones are facing towards the houses, “NO PARKING” will be in effect.
  • Residents should anticipate slight delays on your commute times.

Peirce Street:

  • THERE WILL BE NO SCHEDULED CONSTRUCTION THIS WEEK UNTIL THE WEEK OF 5/20.
  • Installation of the new water main will begin after installation has been completed on Clark Street and Gale Street.
  • Please be aware of “NO PARKING” signs on the street.
    • Note: When the signs on the barrel cones are facing out towards the street “NO PARKING” will be in effect on the posted signs. When the signs on the barrel cones are facing towards the houses, “NO PARKING” will be in effect.
  • Residents should anticipate slight delays on your commute times.

Gale Street:

  • THERE WILL BE NO SCHEDULED CONSTRUCTION THIS WEEK UNTIL THE WEEK OF 5/20.
  • Installation of the new water main will be completed today 5/10. There will be a crew next week on Tuesday and Thursday to test and disinfect the newly installed water main.
  • Installation of water services will begin the week of 5/20. 
  • We do ask that cars parked on the Gale Street not park on the street between the construction hours posted on the barrel cones.
  • Please be aware of “NO PARKING” signs on the street.
    • Note: When the signs on the barrel cones are facing out towards the street “NO PARKING” will be in effect on the posted signs. When the signs on the barrel cones are facing towards the houses, “NO PARKING” will be in effect.
  • Residents should anticipate slight delays on your commute times.

River Street:

  • THERE WILL BE NO SCHEDULED CONSTRUCTION THIS WEEK UNTIL THE WEEK OF 5/20.
  • Construction of new water main installation at the intersections with Ripley Street, Peirce Street, and Gale Street has been completed. Work in the intersections is not completely done and the Contractor will be back in the intersections at a later date.
  • We do ask that cars parked on the Clark Street to not park on Clark Street between the construction hours posted on the barrel cones.
  • Please be aware of “NO PARKING” signs on the street.
    • Note: When the signs on the barrel cones are facing out towards the street “NO PARKING” will be in effect on the posted signs. When the signs on the barrel cones are facing towards the houses, “NO PARKING” will be in effect.
  • Residents should anticipate slight delays on your commute times

Please note that all construction schedules are tentative and subject to change.  They are especially weather dependent. If there are any questions or concerns, please email ewong@city.waltham.ma.us at any time.  If there are immediate concerns, you may call the Engineering Department at 781-314-3830.

PROJECT DESCRIPTION:

This project will consist of various water and sewer improvements to Gale, Ripley, Peirce, and Clark Street.  Once all utility improvements have been completed, roadway paving will occur after utility work has been completed. 

The City has awarded this project N. Granese & Sons, Inc. of Salem, MA.  It is anticipated that utility construction will begin March 2024.  Roadway repaving will occur after utility work has been completed. 

The City will be sending out regular email updates to residents.  In order to sign up for these updates please send an email to ewong@city.waltham.ma.us to be added to the distribution list.

Should you have any questions, you can call us at 781-314-3830 or e-mail at ewong@city.waltham.ma.us.

Trash & recycling will be picked up on the regularly scheduled day during construction.  There may be times where trash and recycling pick up first thing in the morning to avoid conflicts with construction activity.  Please make sure that your trash and recycling is placed curbside by 7:00am on the day of pick up to ensure collection.  

Work hours will be 7:00 AM - 4:00 PM. Please be on the look out for "No Parking" signs posted ahead of work each day.

Should you have any questions, you can call us at 781-314-3830 or email at ewong@city.waltham.ma.us