 Elevators $ 500,000

Project Information:

Owner’s Project Manager: LeftField, LLC

Designer: SMMA

Construction Manager: Consigli Construction Company, Inc.

Estimated Total Construction Cost: $295,000,000

Estimated Trade Contractor Construction Duration: October 2021 – May 2024

Scheduled Overall Occupancy: August 2024

Overall Project Completion: August 2024

SOQ’s must conform to the requirements set forth in the RFQ. The complete RFQ including directions will be available for download as of Wednesday, March 17, 2021 at 8:00 AM at: https://www.dropbox.com/sh/zc9mcrgcwfcp4pk/AAAA7nplJ7l90N4z1qNH0yjra?dl=0

SOQ’s must be submitted at or before 2:00 PM on Wednesday, March 31, 2021, at the following location: LeftField, LLC, 800 Hingham Street, Suite 101AN, Rockland, MA 02370. Please direct any questions by email only to lstapleton@leftfieldpm.com before Wednesday, March 25, 2021 at 5:00 PM. Prospective Respondents shall not communicate with any person or entity participating on the Prequalification Committee at any time during the RFQ