The plan for Lexington Street is as follows, weather permitting:
Tuesday, December 4th - Wednesday, December 5th: Raising structures (CB, manholes, gates)
Thursday, December 6th - Friday, December 7th: Milling areas, cutting in side roads, patching and leveling areas
Monday, December 10th: Paving