As part of the area 5a relief sewer & sewer rehab project, the Waltham Engineering Department will be milling Forest Street and Beaver Street this week in preparation for paving next week

The tentative schedule for roadway milling is as follows (weather permitting):

• Monday, October 22nd: Forest Street
• Tuesday, October 23rd: Forest Street, Forest Circle, Rogers Way
• Wednesday, October 24th: Beaver Street, Gentleman's Way
• Thursday, October 25th: Beaver Street, Valley View Road

Work on Beaver Street and Forest Street will run from 9am-4pm. All other roadways work will run from 7am-5pm. The roadways will remain open during milling activity. Expect traffic delays. Final roadway paving is expected to begin Monday, October 29th.

See here for more info on the project: 
https://www.city.waltham.ma.us/engineering/pages/beaver-street-area-5a & contact John Martino of the Engineering Department at 781-314-3828 or jmartino@city.waltham.ma.us if you have any questions/concerns