Activity will be continuing this week, July 15th - July 19th, to make way for the new Moody Street Fire Station! Here's the schedule of work:

• 7/15 - Monument Removal and No parking on site for Firemen in the construction area

• 7/15 - There will be activity at Fitch School parking lot as it will be used for Parking of construction workers. They will not use the site on Tuesdays to make way for the Farmer's Market

• 7/15 - Signs for cross walk redirect on Moody St and Maple St will go up this week to give citizens time to adjust and to give time for communication ahead of sidewalk closures. (Sidewalks and parking in front of site will be closed on 7/22 with redirection in place)

• 7/16 - 7/19 Demo of "officers quarters' in rear of building will take place all week through Friday