FERNALD APPLICATION: 1/19/2023 Meeting & Follow Up

The Waltham Conservation Commission approved an Order of Conditions for this project on 2 March 2023, which was issued on 16 March 2023.

On 28 March 2023, the City of Waltham submitted a Request for Departmental Action (appeal) of the order of conditions to the MassDEP Northeast Regional Office, requesting that DEP issue a Superseding Order of Conditions. DEP held a public site visit with representatives of the city and the conservation commission on 8 May 2023. As of 24 May 2023, DEP has not yet issued any findings or a ruling.

The version of the plans submitted for the initial 19 January 2023 meeting is located here.

Agendas and minutes of prior meetings can be found on the right side of the main Conservation Commission page of the city web site.

NOTE: On 26 June 2023 the City of Waltham notified MA DEP that it was withdrawing this application. DEP confirmed receipt of this request and considers the file closed as of 20 July 2023..