Cedarwood SSO Mitigation Project

-A A +A

Cedarwood Project Schedule Update:

Update: 06/08/17

This project is substantially complete. Approximately 140,000 gallons/day of Infiltration and Inflow has been removed. 

Remaining work: Traffic marking (painting), paving (mill & overlay) on three streets, Stow Street - Milton Street to Tavern Square, Milton Street and Caldwell Street.

Watch here for date soon!

Please contact  John Martino of the Engineering Department by phone, 781-314-3828 or email, jmartino@city.waltham.ma.us if you have any questions.